Johnson Candies and Gifts

Software Project Status Online Report

Description

 

 

CUSTOMER

QUALITY APPS

END-USER

Input

Process

Output

Need (Requirements)

Feasibility

 Planning

 Requirements Analysis

System Design

Code & Unit Test

System Test

Release

Post-Mortem

Solution (Application)

 

 

Requirements Document

Milestones

Milestone

Date

Project Start Date

9/2006

Initial Customer Meeting

9/13/2006

Software Feasibility Plan Due

9/20/2006

Spiral 1 Completion – Prototype 1

10/11/2006

Spiral 2 Completion – Prototype 2

11/1/2006

Spiral 3 Completion – Interim System

11/10/2006

Spiral 4 Completion – Final System

11/21/2006

Acceptance Test

11/23/2006

Go Live

11/28/2006

Project Outbrief/Final Report

11/29/2006

Risks

Risks

Probability

Impact

Mitigation Plan

Integration of software with hardware

High

Severe

Test early and often

Integration of FacePrint (in C#) with some dlls written in Java

High

Severe

Be prepared to write wrapper classes to make it compatible

Communication with customer

Medium

Severe

Be accessible to the customer in as many forms as possible

Reliability of libraries

Medium

Moderate

Test functionality of libraries as early as possible

Personnel skills

Medium

Low

Limit scope, begin development as early as possible

FacePrint User Stories

Stories Spiral 1 Spiral 2 Spiral 3 Spiral 4
Get Enrolled / Perform Enrollment   X    
Get Identified / Perform Identification     X  
Get Verified / Perform Verification     X  
Database Maintenance   X    
Re-Enrollment   X    
Perform Calibration     X  
Generate Reports       X
Grant Access for Special Cases       X

Documents

Project Calendar

 
Project Schedule  
Requirements Questionnaire  
Software Feasibility Plan 20 Sep 2006
Spiral 1 Software Documentation 11 Oct 2006
Spiral 1 Presentation 11 Oct 2006
Spiral 2 Software Documentation 1 Nov 2006
Spiral 2 Presentation 1 Nov 2006
Spiral 3 Software Documentation 10 Nov 2006
Spiral 3 Presentation 10 Nov 2006
Spiral 4 Software Documentation 21 Nov 2006
Spiral 4 Presentation 21 Nov 2006

Metrics

- Defects (Problem Reports)

- Changes (Change Requests)

Build Status